{"id":13738,"date":"2022-10-19T16:49:00","date_gmt":"2022-10-19T14:49:00","guid":{"rendered":"https:\/\/aedic.eu\/?p=13738"},"modified":"2024-06-15T15:27:10","modified_gmt":"2024-06-15T13:27:10","slug":"diga-di-nachtigal-centro-africa-i-lavori-di-costruzione-procedono-al-ritmo-del-145-in-soli-5-mesi","status":"publish","type":"post","link":"https:\/\/aedic.eu\/en\/africa-central\/dam-of-nachtigal-centre-africa-construction-work-proceeds-at-a-rhythm-of-145-in-only-5-months\/","title":{"rendered":"Nachtigal Dam Central Africa: Construction progresses at a rate of 14.5% in just 5 months"},"content":{"rendered":"<p>The hydroelectric company Nachtigal, the administrator of the project in September 2022, stated that the project has already been completed at 74.5%.<\/p>\n\n\n\n<p>Last April, progress was estimated at 60%. Over the past few months, construction work has accelerated greatly, with the construction of the dam that will meet the energy consumption of the central region of Cameroon being completed at 74.5%.<\/p>\n\n\n\n<p>La <a href=\"https:\/\/aedic.eu\/en\/business-in-africa\/besix-group-wins-contract-for-construction-of-electrical-power-station-of-nachtiga\/\">construction of the Nachtigal hydroelectric dam<\/a>located in Batchenga, is progressing at a steady pace. In the past five months, they have developed remarkably, according to data officialised by the Nachtigal hydro power company (Nhpo) at the end of September 2022.<\/p>\n\n\n\n<p>The company managing the project indicates on its website that civil engineering works have already been completed for 74.5%. For the rest, the rate of progress <a href=\"https:\/\/aedic.eu\/en\/doing-business-in-africa\/africa-growth-of-42-reported-by-cameroon-in-the-first-quarter-of-2019\/\" >recorded since the first<\/a> April valuation is 14.5%.<\/p>\n\n\n\n<p>In other words, the rate of progress recorded since the first evaluation in April 2005 is 14.5%, since at that time the site's execution rate was estimated at 4 60%. This is the best progress <a href=\"https:\/\/aedic.eu\/en\/sports\/cup-africa-changes-the-jobs-in-cameroon\/\" >of works<\/a> on the site to date.<\/p>\n\n\n\n<p>This was the best progress of work on the site in the last ten months. In fact, at the end of the year 2021, when <strong>Energy Minister Gaston Eloundou Essomba<\/strong> visited the site, the completion rate was still at 51.7%.<\/p>\n\n\n\n<p>The civil works still have to be completed, as does the electromechanical part, which has a completion percentage of 69.5%. <\/p>\n\n\n\n<p>As far as the transmission line and the operating site lots are concerned, they have already been completed. The least that can be said is that work on the Nachtigal dam site has never progressed as quickly as it has in the last ten months. <\/p>\n\n\n\n<p>Over the past two and a half years, the work programme had been severely disrupted by several contingencies, including the Covid-19 pandemic, which<br>inevitably caused delays in the execution of the work, there were also numerous strikes by employees demanding better working conditions. <\/p>\n\n\n\n<p>The Nhpc company has been challenged on several occasions by NGOs and the affected local communities living in the area. <\/p>\n\n\n\n<p>The objections to the project are related to the impact the dam will have on the environment and for other agreements that the company had made with the local people and which it has not fulfilled.<\/p>\n\n\n\n<div style=\"height:100px\" aria-hidden=\"true\" class=\"wp-block-spacer\"><\/div>\n\n\n\n<h3 class=\"has-text-align-center wp-block-heading\" id=\"block-f640ab86-1dd9-47fc-9bbf-2bf15609f5d0\">what do you want to do now?<\/h3>\n\n\n\n<p id=\"block-ed3000bd-d577-4ac4-8863-93b5cb587a3e\"><strong>Do you want to stay in Europe with a recession just around the corner, galloping inflation and rising gas and electricity costs, and lack of raw materials, or do you want to get in touch with us to develop your business opportunity in Central Africa? <\/strong><\/p>\n\n\n\n<p id=\"block-ed3000bd-d577-4ac4-8863-93b5cb587a3e\"><strong>If you would like to know more, please fill in the form below and one of our consultants will contact you within 24 hours.<\/strong><\/p>\n\n\n\n<div class=\"wp-block-contact-form-7-contact-form-selector\">\n<div class=\"wpcf7 no-js\" id=\"wpcf7-f13704-o1\" lang=\"it-IT\" dir=\"ltr\">\n<div class=\"screen-reader-response\"><p role=\"status\" aria-live=\"polite\" aria-atomic=\"true\"><\/p> <ul><\/ul><\/div>\n<form action=\"\/en\/wp-json\/wp\/v2\/posts\/13738#wpcf7-f13704-o1\" method=\"post\" class=\"wpcf7-form init\" aria-label=\"Contact form\" novalidate=\"novalidate\" data-status=\"init\" data-trp-original-action=\"\/en\/wp-json\/wp\/v2\/posts\/13738#wpcf7-f13704-o1\">\n<div style=\"display: none;\">\n<input type=\"hidden\" name=\"_wpcf7\" value=\"13704\" \/>\n<input type=\"hidden\" name=\"_wpcf7_version\" value=\"5.9.8\" \/>\n<input type=\"hidden\" name=\"_wpcf7_locale\" value=\"it_IT\" \/>\n<input type=\"hidden\" name=\"_wpcf7_unit_tag\" value=\"wpcf7-f13704-o1\" \/>\n<input type=\"hidden\" name=\"_wpcf7_container_post\" value=\"0\" \/>\n<input type=\"hidden\" name=\"_wpcf7_posted_data_hash\" value=\"\" \/>\n<input type=\"hidden\" name=\"_wpcf7_recaptcha_response\" value=\"\" \/>\n<\/div>\n<p><label> Your Name<br \/>\n<span class=\"wpcf7-form-control-wrap\" data-name=\"your-name\"><input size=\"40\" maxlength=\"400\" class=\"wpcf7-form-control wpcf7-text wpcf7-validates-as-required\" aria-required=\"true\" aria-invalid=\"false\" value=\"\" type=\"text\" name=\"your-name\" \/><\/span> <\/label>\n<\/p>\n<p><label> Your email<br \/>\n<span class=\"wpcf7-form-control-wrap\" data-name=\"your-email\"><input size=\"40\" maxlength=\"400\" class=\"wpcf7-form-control wpcf7-email wpcf7-validates-as-required wpcf7-text wpcf7-validates-as-email\" aria-required=\"true\" aria-invalid=\"false\" value=\"\" type=\"email\" name=\"your-email\" \/><\/span> <\/label>\n<\/p>\n<p><label> Phone <span class=\"wpcf7-form-control-wrap\" data-name=\"tel-483\"><input size=\"40\" maxlength=\"400\" class=\"wpcf7-form-control wpcf7-tel wpcf7-validates-as-required wpcf7-text wpcf7-validates-as-tel\" aria-required=\"true\" aria-invalid=\"false\" value=\"\" type=\"tel\" name=\"tel-483\" \/><\/span> <\/label>\n<\/p>\n<p><label> Select interest<br \/>\n<span class=\"wpcf7-form-control-wrap\" data-name=\"menu-739\"><select class=\"wpcf7-form-control wpcf7-select wpcf7-validates-as-required\" aria-required=\"true\" aria-invalid=\"false\" multiple=\"multiple\" name=\"menu-739[]\"><option value=\"Ricerca tender \/ Appalti in africa MDBs\">Search Tenders \/ Procurement in Africa MDBs<\/option><option value=\"Costituzione NewCo\">Establishment of NewCo<\/option><option value=\"Ricerca partner locale in Africa\">Local partner search in Africa<\/option><option value=\"Consulenza Aziendale\">Corporate Consulting<\/option><option value=\"Apertura conto corrente in Africa\">Opening a current account in Africa<\/option><option value=\"Ricerca Finanziamenti e Assicurazioni in Africa\">Search for finance and insurance in Africa<\/option><option value=\"Ricerca Finanziamento Banca di sviluppo europea\">Research Funding European Development Bank<\/option><option value=\"Internazionalizzazione d&#039;Impresa\">Business Internationalisation<\/option><option value=\"Investimento immobiliare\">Real estate investment<\/option><option value=\"IDE\">IDE<\/option><option value=\"VISA\">VISA<\/option><option value=\"Altro...\">More...<\/option><\/select><\/span><\/label>\n<\/p>\n<p><label> Object<br \/>\n<span class=\"wpcf7-form-control-wrap\" data-name=\"your-subject\"><input size=\"40\" maxlength=\"400\" class=\"wpcf7-form-control wpcf7-text wpcf7-validates-as-required\" aria-required=\"true\" aria-invalid=\"false\" value=\"\" type=\"text\" name=\"your-subject\" \/><\/span> <\/label>\n<\/p>\n<p><label> Your message (optional)<br \/>\n<span class=\"wpcf7-form-control-wrap\" data-name=\"your-message\"><textarea cols=\"40\" rows=\"10\" maxlength=\"2000\" class=\"wpcf7-form-control wpcf7-textarea\" aria-invalid=\"false\" name=\"your-message\"><\/textarea><\/span> <\/label>\n<\/p>\n<p><label>GDPR Privacy and Cookies Consent (required)<br \/>\n<span class=\"wpcf7-form-control-wrap\" data-name=\"acceptance-52\"><span class=\"wpcf7-form-control wpcf7-acceptance\"><span class=\"wpcf7-list-item\"><label><input type=\"checkbox\" name=\"acceptance-52\" value=\"1\" checked=\"checked\" aria-invalid=\"false\" \/><span class=\"wpcf7-list-item-label\">I give my consent<\/span><\/label><\/span><\/span><\/span> to the processing of my data for the purposes of their treatment and I confirm that I have read the privacy policy of the site.<br \/>\n<\/label>\n<\/p>\n<span class=\"wpcf7-form-control-wrap recaptcha\" data-name=\"recaptcha\"><span data-sitekey=\"6Lc19QseAAAAACVPU2tihU5dPZL9q67S82EoxVYJ\" class=\"wpcf7-form-control wpcf7-recaptcha g-recaptcha\"><\/span>\r\n<noscript>\r\n\t<div class=\"grecaptcha-noscript\">\r\n\t\t<iframe loading=\"lazy\" src=\"https:\/\/www.google.com\/recaptcha\/api\/fallback?k=6Lc19QseAAAAACVPU2tihU5dPZL9q67S82EoxVYJ\" frameborder=\"0\" scrolling=\"no\" width=\"310\" height=\"430\">\r\n\t\t<\/iframe>\r\n\t\t<textarea name=\"g-recaptcha-response\" rows=\"3\" cols=\"40\" placeholder=\"reCaptcha Response Here\">\r\n\t\t<\/textarea>\r\n\t<\/div>\r\n<\/noscript>\r\n<\/span>\n<p><input class=\"wpcf7-form-control wpcf7-submit has-spinner\" type=\"submit\" value=\"Send\" \/>\n<\/p><div class=\"wpcf7-response-output\" aria-hidden=\"true\"><\/div>\n<input type=\"hidden\" name=\"trp-form-language\" value=\"en\"\/><\/form>\n<\/div>\n<\/div>","protected":false},"excerpt":{"rendered":"<p>The hydroelectric company Nachtigal, the administrator of the project in September 2022, stated that the project has already been completed at 74.5%. Last April, progress was estimated at 60%. Over the past few months, construction work has accelerated greatly, the construction of the ... <\/p>\n<p class=\"read-more-container\"><a title=\"Nachtigal Dam Central Africa: Construction progresses at a rate of 14.5% in just 5 months\" class=\"read-more button\" href=\"https:\/\/aedic.eu\/en\/africa-central\/dam-of-nachtigal-centre-africa-construction-work-proceeds-at-a-rhythm-of-145-in-only-5-months\/#more-13738\" aria-label=\"More on Nachtigal Dam Central Africa: Construction progresses at a rate of 14.5% in just 5 months\">Read more<\/a><\/p>","protected":false},"author":1,"featured_media":13743,"comment_status":"closed","ping_status":"open","sticky":false,"template":"","format":"standard","meta":{"_acf_changed":false,"iawp_total_views":16,"footnotes":""},"categories":[412],"tags":[],"acf":[],"_links":{"self":[{"href":"https:\/\/aedic.eu\/en\/wp-json\/wp\/v2\/posts\/13738"}],"collection":[{"href":"https:\/\/aedic.eu\/en\/wp-json\/wp\/v2\/posts"}],"about":[{"href":"https:\/\/aedic.eu\/en\/wp-json\/wp\/v2\/types\/post"}],"author":[{"embeddable":true,"href":"https:\/\/aedic.eu\/en\/wp-json\/wp\/v2\/users\/1"}],"replies":[{"embeddable":true,"href":"https:\/\/aedic.eu\/en\/wp-json\/wp\/v2\/comments?post=13738"}],"version-history":[{"count":6,"href":"https:\/\/aedic.eu\/en\/wp-json\/wp\/v2\/posts\/13738\/revisions"}],"predecessor-version":[{"id":13926,"href":"https:\/\/aedic.eu\/en\/wp-json\/wp\/v2\/posts\/13738\/revisions\/13926"}],"wp:featuredmedia":[{"embeddable":true,"href":"https:\/\/aedic.eu\/en\/wp-json\/wp\/v2\/media\/13743"}],"wp:attachment":[{"href":"https:\/\/aedic.eu\/en\/wp-json\/wp\/v2\/media?parent=13738"}],"wp:term":[{"taxonomy":"category","embeddable":true,"href":"https:\/\/aedic.eu\/en\/wp-json\/wp\/v2\/categories?post=13738"},{"taxonomy":"post_tag","embeddable":true,"href":"https:\/\/aedic.eu\/en\/wp-json\/wp\/v2\/tags?post=13738"}],"curies":[{"name":"wp","href":"https:\/\/api.w.org\/{rel}","templated":true}]}}